The following describes the work [Company] proposes to perform on the [Project Name] project located at [Address]. This scope is based on plans dated [Date] and specifications dated [Date], and reflects all addenda through Addendum [#].
Included
- Furnish all labor, materials, equipment, and supervision necessary to complete the cast-in-place concrete scope of work as shown on Sheets [list]
- Excavation and backfill of footings to neat lines, including spoil placement on site
- Formwork, rebar (per included rebar schedule), concrete placement, and finishing
- Standard saw cuts and control joints per plans
- Cylinder break testing coordination with owner's testing agency
- Cold weather protection through [date]
- Hot weather curing during summer placements
- One mobilization for footings; one mobilization for slab; one mobilization for [other]
- Layout from owner-provided control points and benchmarks
Excluded
- Survey and layout beyond initial transfer from control
- Permits, fees, and bonds
- Topsoil strip and stockpile
- Mass excavation and grading
- Soil treatment, dewatering, or shoring
- Embeds, anchor bolts, or sleeves not specifically called out
- Sealants, joint filler, or hardener (specify if required)
- Temporary heat or weather enclosures beyond standard frost protection
- After-hours premium or weekend overtime
- Repair of work damaged by other trades
- Any work required by addenda issued after [date]
Clarifications
- Concrete mix designs are based on standard specifications. Custom mixes will be priced as a change.
- Form release, curing compounds, and finishing materials are standard products. Owner-specified premium products will be priced as a change.
- This proposal is valid for [30] days from the date issued.
Pricing
| Scope | Price |
|---|---|
| Footings & foundations | $___ |
| Slab on grade | $___ |
| Walls / columns | $___ |
| Site concrete | $___ |
| Total Base Bid | $___ |
Alternates priced separately on the attached schedule.
Submitted by: [Name, Title] Date: [Date] Bid #: [###]