The document you write last and need most
The scope letter is the page nobody reads at bid time and everybody reads at change-order time. It's also the only document that travels with your bid into the project file. Get it right and you have a defense. Get it wrong and every gap becomes your problem.
After fifteen years of writing them, losing arguments about them, and rewriting them on Sunday nights, here's the structure that holds up.
Open with what you are bidding
Don't make the GC hunt for it. Line one of the letter should answer the question: "What is this contractor pricing?"
Bedrock Concrete is pleased to submit our proposal for the cast-in-place concrete scope of work for the [project name] project, dated [bid date], based on plans dated [plan date] and addenda 1 through [last addendum number].
Three things in that sentence matter:
- 1.Scope name — not "concrete," but "cast-in-place concrete." If precast is in the package, you're not bidding it unless you say so.
- 2.Bid date — anchors which version of your pricing this is.
- 3.Plan and addendum dates — anchors which version of the documents your pricing is based on. If a new addendum drops after, every change is a re-price, not a sour conversation.
List inclusions before exclusions
GCs read inclusions. They skim exclusions. Put your scope first, in plain language, organized by trade flow.
A good inclusion list for concrete looks like:
- All cast-in-place concrete shown on structural sheets S1.1 through S4.3
- Reinforcing steel furnished and installed per drawings and ACI 318
- Formwork, shoring, and bracing for all listed scope
- Anchor bolt installation (templates and survey by others — see exclusions)
- Concrete curing per spec section 03 39 00
- Slab finishing to specified flatness (FF35, FL25) for warehouse slabs
Notice what's missing? Generic phrases like "all work shown on drawings" or "complete concrete scope." Don't use them. They look comprehensive and read as ambiguous.
Then list exclusions, by line
Exclusions are the part of the letter the GC will challenge. Make every one specific. "Excludes underslab utilities" is weaker than "Excludes all underslab plumbing, electrical, and mechanical conduits; final coordination drawings to be provided by GC two weeks prior to slab pour."
Common exclusions worth being explicit about:
- Anchor bolt templates and field survey
- Embedded plates, weld plates, and anchor channels (furnished by steel)
- Vapor barrier under slab (specify who provides if you're not)
- Granular base course
- Saw-cutting other than typical control joints
- Joint sealant
- Concrete testing by independent lab
- Winter heat and protection beyond [X] degrees
- Hoisting and pumping over [X] floors
- Permits and impact fees
- Bonds and insurance beyond standard GL coverage
Every one of these has been the subject of a change order on a real project. Listing it doesn't make you difficult. It makes you clear.
The qualifications section
After exclusions, add a qualifications section. This is where you list the assumptions your pricing depends on. Common ones:
- Continuous access to the pour area during scheduled operations
- Adequate laydown and parking within 200 feet of pour location
- Tower crane availability for placing rebar on elevated decks
- Mud mat or stable subgrade provided by site contractor
- Schedule based on [X] working days, single shift, Monday through Friday
The point of qualifications isn't to escape work. It's to make the conditions of your price legible. If the GC accepts the bid, they accept the qualifications.
The unit-rate section
For change-order protection, attach unit rates for the work most likely to grow:
- Additional CY of concrete (slab, wall, footing, pier — each separately)
- Additional LF of formwork
- Additional tons of rebar
- Additional CY of demolition and disposal
When the change order comes (and it will), the conversation goes from "what's it worth" to "multiply our agreed unit rate by the new quantity." Twenty minutes instead of two weeks.
Sign and date it
The scope letter is a legal document. It needs your name, title, signature, and date. Without those, it's an opinion piece.
One last rule
The day after you submit, read the scope letter as if you were the GC reading it for the first time. If you find anything ambiguous, file the corrected version with the GC by email before they award. It's allowed. It's smart. And it's a lot cheaper than arguing about it in month four.
See also: The 90-minute pre-submit ritual every concrete estimator should run · The proposal as a sales document