Worksheet contents
Tab 1: Cut/fill grid
A 10×10 grid (expandable) with existing elevation, proposed elevation, delta, and area. Computes BCY by grid square and totals.
Tab 2: Shrink/swell
Apply per-soil-type shrink/swell factors to convert BCY to LCY (loose) and CCY (compacted).
Tab 3: Topsoil strip
SF × depth × bulking factor for stockpile or haul-off.
Tab 4: Over-excavation
Footing and slab over-ex volumes for select fill placement.
Tab 5: Haul cycle calculator
- Truck capacity (CY per load)
- Loaded haul speed
- Empty return speed
- Round-trip distance
- Loading time
- Dump time
Outputs: cycles per hour per truck, total truck-hours required, fleet size for given duration.
Tab 6: Equipment summary
Excavator hours, dozer hours, compactor hours, water truck hours, foreman hours. Roll up to total equipment cost.
How to use
This is a check tool, not your bid. For sitework specialists with dedicated cut/fill scope, use a real earthwork platform. For concrete and earthwork contractors who do occasional dirt scope, this gets you a defensible number in 30 minutes.
Always document the assumptions in your bid notes — soil type, shrink/swell factor used, haul distance assumption, dump fee per CY.