Definition
Soil volume changes depending on its state:
- Bank Cubic Yards (BCY): in-place, undisturbed.
- Loose Cubic Yards (LCY): excavated, in a truck or stockpile.
- Compacted Cubic Yards (CCY): placed and compacted to specification.
The conversion factors between states are called shrink/swell (or "load factor" and "shrinkage factor").
Typical factors
(varies by soil type, always verify with the geotech)
- Common earth: swell ~25%, shrink ~10%
- Clay: swell ~25–35%, shrink ~10–20%
- Sand: swell ~10–15%, shrink ~5%
- Rock: swell ~50–75%, shrink negligible
Why it matters in bids
If you're hauling 100 BCY of cut, you're loading ~125 LCY in trucks. If you're placing 100 CCY of fill, you need ~110–125 BCY of borrow material.
Forget to apply the conversion and you're either short trucks or short fill on the job.