Excavation and utility trench takeoff: the quantities that matter

Trench excavation, bedding, pipe zone and backfill, depth brackets and spoil: how to take off utility and structure excavation so the dig and the haul are both in the bid.

Mass grading gets the attention, but on a lot of sites the money is in the trenches. A trench takeoff is a few quantities, each with its own price: excavation, bedding, pipe zone backfill, backfill to grade, spoil, and the trench support it takes to dig it safely.

Trench excavation

Trench volume is the trench's cross-section times its length. The cross-section depends on three things:

  • Depth. From the surface to the bottom of the bedding. Take it from the pipe inverts on the profile, or from minimum cover where there's no profile. The surface matters: dig before grading and you start at existing ground, dig after and you start at finished grade.
  • Width at the bottom. The pipe's outside diameter plus working room each side, often set by the spec.
  • Side slopes. Vertical walls with a trench box or shoring, or sloped sides such as 1/2:1, 1:1 or 1 1/2:1, depending on soil and depth.

A sloped trench is a trapezoid: average width times depth. Break long runs at manholes and wherever the depth changes much, and total them.

Depth brackets

Production and price change with depth, so most estimators group trench by depth: 0 to 4 feet, 4 to 6, 6 to 8, 8 to 10, and so on. Deeper trench costs more per foot to dig, needs support, and slows the crew.

Bedding, pipe zone and backfill

  • Bedding under the pipe, in imported material.
  • Pipe zone backfill around and just over the pipe, often select fill.
  • Backfill to grade, often site soil, compacted in lifts.

The pipe's own volume comes out of the trench; on large pipe it's a real number.

Structures and spoil

Manholes, catch basins and vaults get their own excavation and backfill. Then the spoil: whatever the bedding, pipe and select fill displace has to go somewhere, which is either export or room in the site's fill.

How Bedrock does it

In Earthwork Pro you lay out storm, sewer, water, gas, electric and communications runs with their structures, then set each trench: pipe material and size, depth by inverts or by cover, dug before or after grading, side slopes or working room, bedding and pipe zone backfill. Depth brackets default to 4, 6, 8 and 10 feet and can be changed, and a trench cutaway shows the deepest and least-cover points. Trench excavation and bedding go to the estimate with the site's cut and fill.

For footings, pads and basements, the earthwork starter assemblies cover structural excavation and backfill, priced as you trace. See Earthwork Pro.

Questions

How do you calculate trench excavation?

Multiply the trench's cross-section by its length. The cross-section is the bottom width plus the side slopes, times the depth from the surface to the bottom of the bedding. Break runs where the depth changes and total them.

What are trench depth brackets?

Ranges of depth, such as 0 to 4 feet and 4 to 6 feet, that trench is grouped and priced by, because digging gets slower and needs more support as it gets deeper.

Does Bedrock take off utility trenches?

Yes. Earthwork Pro takes off storm, sewer, water and dry utility trenches with their structures, by inverts or by cover, with side slopes, bedding and pipe zone backfill, and sends the quantities to the estimate.