Shrink / Swell

The volume change of soil between in-place (bank), loose (loaded), and compacted states.

Definition

Soil volume changes depending on its state:

  • Bank Cubic Yards (BCY): in-place, undisturbed.
  • Loose Cubic Yards (LCY): excavated, in a truck or stockpile.
  • Compacted Cubic Yards (CCY): placed and compacted to specification.

The conversion factors between states are called shrink/swell (or "load factor" and "shrinkage factor").

Typical factors

(varies by soil type, always verify with the geotech)

  • Common earth: swell ~25%, shrink ~10%
  • Clay: swell ~25–35%, shrink ~10–20%
  • Sand: swell ~10–15%, shrink ~5%
  • Rock: swell ~50–75%, shrink negligible

Why it matters in bids

If you're hauling 100 BCY of cut, you're loading ~125 LCY in trucks. If you're placing 100 CCY of fill, you need ~110–125 BCY of borrow material.

Forget to apply the conversion and you're either short trucks or short fill on the job.

See: Cut and fill estimating without the mystery