Sitework import and export numbers on tight bids

Cut and fill never balance on the first take. Here's how earthwork estimators handle import, export, and the truck math that decides whether your bid is a winner or a casualty.

The numbers that decide the bid

On most commercial earthwork bids, the dirt itself isn't what wins or loses you the job. It's the trucks. Import and export costs swing harder than any other line item on a sitework bid, and they're the easiest to get wrong because nobody on the plan tells you where the dirt is going.

After 20 years of bidding earthwork across four states, here's how we actually think about it.

Step one: don't trust the geotech report's swell number

Every geotech report gives you a swell factor. Use it as a starting point, not a final number. The real swell depends on:

  • Soil type — clay swells 25–40%, silty sand 15–25%, well-graded gravel 10–15%
  • Moisture at excavation — wet soil swells less but weighs more, both bad for trucks
  • How it's loaded — a 30 CY scraper compacts the load. A loader-fed truck doesn't.

If you bid the swell at 15% and the field hits 28%, you're paying for extra trucks out of your own pocket. We add 3–5% on top of the geotech swell unless we've worked the same soil before.

Step two: figure out where the dirt is actually going

Plans show cut and fill in CY. They almost never show:

  • Whether onsite stockpile space exists
  • Whether the import borrow source is permitted
  • Whether the export site accepts the soil class
  • What the haul distance round-trip actually is

Before you finalize the bid, call the dump site. Confirm they take the soil. Confirm the tipping fee. Confirm hours of operation. We've seen bids lose 6% margin because the closest accepting site closed at 3pm and the trucks had to run a longer route after lunch.

Step three: do the truck math twice

Truck math is the part that estimators rush. Don't.

The right calculation:

  • Truck capacity — Use legal payload for your state, not nominal. A 14 CY truck in California carries 12 CY legal in most counties.
  • Cycle time — Load (5 min) + Haul (depends) + Dump (3 min) + Return (depends) + Queue (10 min realistic).
  • Trucks per hour — 60 / cycle time in minutes.
  • CY per hour — Trucks per hour × payload.
  • Total hours — Total CY / CY per hour.
  • Total cost — Hours × hourly rate (or trucks × day rate, whichever your local market uses).

Now do it again with a 15% productivity loss for queuing, breakdowns, and the inevitable rain day. That second number is your bid number.

Step four: balance, then check, then balance again

Even when the plan shows a perfect cut-fill balance, the field rarely matches. Two reasons:

  1. 1.The geotech compaction factor for fill is almost always optimistic. If the report says 92% compaction is achievable, expect to need 8–12% more import than the cut volume suggests.
  2. 2.You can't use everything you cut. Topsoil, organics, oversized rock, contaminated layers — all of it has to come out and get replaced. The plan rarely subtracts these.

Our rule: a "balanced" site on paper is usually a 5–8% net import job in practice. Bid it that way and the field doesn't surprise you.

Step five: the contingency conversation

Some GCs will let you carry an import allowance with a unit rate. Others want a fixed lump sum. Both are fine. What's not fine is carrying a fixed lump sum without protecting yourself with a contract clause for material changes in subgrade conditions.

If the contract doesn't let you adjust for differing conditions, your contingency needs to be bigger. We use:

  • Known balanced site, clean geotech: 5% contingency
  • Balanced site, unknown subgrade: 10% contingency
  • Net import job, suburban borrow source: 8% contingency
  • Net export job, regional dump options: 12% contingency
  • Urban site, restricted truck routes, limited dump windows: 15–20% contingency

The mistake that costs the most

The most expensive mistake on earthwork bids isn't a math error. It's not calling the dump site. Spend 20 minutes on the phone before you submit the bid and you'll save 200 hours of arguments later.