Two scopes, one job
If you self-perform both earthwork and concrete on the same project, you have a structural advantage over the GC who's hiring two subs. You also have a structural temptation: bid each scope as if the other isn't there.
That costs you margin in three places.
1. Sequencing
The earthwork crew that grades your foundation pads is the same crew that's going to be paid to wait if your concrete forecaster underestimated the cycle. Bid the sequence, not the scopes.
Bedrock's bid pipeline lets you tag both scopes against the same project, with a shared address, GC, and due date — so when you're rolling forward, you see the job and not two duplicate cards.
2. Equipment overhead
A 320 excavator on the dirt scope is the same machine you'll use to backfill your foundation perimeter. If you load full equipment hours into both bids, you're double-charging the GC and inviting them to value-engineer one scope away.
3. Cash flow
Earthwork pours bill at near-completion. Foundations bill at slab. Concrete superstructure bills monthly. If you bid both scopes without modeling cash flow, you're going to find out in month 3 that the dirt money paid for itself but the concrete is underwater.
The bid posture
When you self-perform both, your bid posture is: we're the safest sequence the GC can buy. Price that. Document it. Make it visible in the proposal — the cover narrative should explicitly mention the integrated dirt-to-slab scope. That's the value the owner is buying. Don't make them guess.