Earthworks takeoff worksheet (XLSX)

Grid-method cut/fill worksheet, plus topsoil strip, over-ex, and haul cycle calculator.

Worksheet contents

Tab 1: Cut/fill grid

A 10×10 grid (expandable) with existing elevation, proposed elevation, delta, and area. Computes BCY by grid square and totals.

Tab 2: Shrink/swell

Apply per-soil-type shrink/swell factors to convert BCY to LCY (loose) and CCY (compacted).

Tab 3: Topsoil strip

SF × depth × bulking factor for stockpile or haul-off.

Tab 4: Over-excavation

Footing and slab over-ex volumes for select fill placement.

Tab 5: Haul cycle calculator

  • Truck capacity (CY per load)
  • Loaded haul speed
  • Empty return speed
  • Round-trip distance
  • Loading time
  • Dump time

Outputs: cycles per hour per truck, total truck-hours required, fleet size for given duration.

Tab 6: Equipment summary

Excavator hours, dozer hours, compactor hours, water truck hours, foreman hours. Roll up to total equipment cost.

How to use

This is a check tool, not your bid. For sitework specialists with dedicated cut/fill scope, use a real earthwork platform. For concrete and earthwork contractors who do occasional dirt scope, this gets you a defensible number in 30 minutes.

Always document the assumptions in your bid notes — soil type, shrink/swell factor used, haul distance assumption, dump fee per CY.