What cut and fill actually requires
To bid a cut and fill scope you need three things:
- 1.The existing ground surface (the existing topo)
- 2.The proposed surface, at subgrade (the grading plan, less pavement, slab and topsoil sections)
- 3.A method to compute the volume between the two
Where the proposed surface is below existing, it's cut; where it's above, it's fill. The three common methods differ only in how they compute that volume.
The grid method
- 1.Overlay a grid on the site (50 ft by 50 ft is a reasonable start for a five-acre site).
- 2.At each grid point, read the existing and proposed elevations and note the difference.
- 3.Average the four corners of each square for its average depth.
- 4.Multiply by the square's area, and sum the squares.
It's simple and checkable by hand, but it misses anything smaller than the grid: a swale, a pad edge, a curb line. A finer grid helps and takes longer.
Average end area
Cut cross-sections at regular stations, measure the cut and fill area on each, and multiply the average of each pair by the distance between them. It's the standard for roads and long linear work, and a good check on any site.
Surfaces (TIN)
Earthwork software builds each surface as a mesh of triangles (a triangulated irregular network, or TIN) through the contours and spot grades, then computes the exact volume between the two meshes. It follows every break in the design, and it's what the machines will grade to. Its accuracy depends on the input: a wrong contour elevation is a spike in the surface and a wrong number in the bid.
Adjustments you can't skip
- Shrink and swell. Fill compacts and cut bulks when it's loaded. A hundred bank yards of fill placed to spec can take 110 to 125 bank yards of borrow, depending on the soil, and a hundred bank yards of cut hauled off is 115 to 135 loose yards in the trucks. Take the factors from the geotechnical report.
- Topsoil strip. Strip and replacement are their own line items, and the stripped depth changes the cut and fill under them.
- Over-excavation. If the geotech calls for removing and replacing soil under footings or slabs, that volume is separate and often bigger than you expect.
- Subgrade prep. Compaction, moisture conditioning and proof rolling aren't inside the cut and fill volume.
- Trenches and structures. Utility trench spoil and structure backfill change what the site has to import or export.
What cut and fill software does
Cut and fill software builds the two surfaces, computes the volumes, and shows you where the cut and fill are so you can check them. The better tools read the plan for you, show the site in 3D, cut sections, plan the haul, and export the surfaces for the surveyor and the machines.
Bedrock's Earthwork Pro does all of that inside an estimating app. It reads contours, their elevation labels and spot grades off the civil PDF for you to review, builds existing and proposed surfaces, models pads, roads, paving, ponds and utility trenches, and gives bank cut, fill and net import or export, with strip, topsoil and over-excavation alongside. On test shapes with known volumes it comes within 0.4% of the exact answer. The quantities go to the job's estimate as line items. See Earthwork Pro, or compare the earthwork takeoff tools.