What you'll have at the end
A Gantt chart for your job, generated from your estimate, with realistic durations based on your crew production rates, the critical path highlighted, and a printable two-week lookahead for the field.
Before you start
You need:
- An estimate with line items priced
- A crew setup attached to each labor-driven assembly (so the scheduler knows how many bodies are on the work)
- A project start date on the Project Setup tab
If you have those three, the rest is automatic.
Step 1 — Open the Schedule tab
In any project, click Schedule in the side rail. If the project has no schedule yet you'll see a single button: Generate from Estimate.
Click it.
Bedrock walks every line item, looks at the quantity, the assigned crew, and the production rate, and computes a duration. Each line item becomes a task. The tasks are ordered by CSI division and sequenced based on construction logic (sitework before footings, footings before walls, walls before slabs, etc.).
You should see a populated Gantt chart in 1–2 seconds.
Step 2 — Sanity check the durations
The generator is a starting point. Glance at the bars and look for obvious busts:
- A 2-day duration on a 40,000 SF slab is wrong (probably a crew size or production rate issue)
- A 60-day duration on a single footing is wrong (probably a quantity unit mismatch)
Click any bar to open the task drawer. You can edit duration, crew, start date, or finish date directly. If you change the duration, the rest of the schedule reflows automatically.
Step 3 — Link the tasks that actually depend on each other
Bedrock auto-creates Finish-to-Start links between tasks in the typical construction sequence. You'll want to tune them.
- Hover the right edge of a predecessor task. A link handle appears.
- Drag from the predecessor to the successor.
- Choose the link type: FS (most common), SS (parallel start), or FF (must finish together).
- Add lag in days if there's a cure time or inspection gap.
The schedule recomputes on every link change. The critical path re-highlights.
Step 4 — Open the line item sidebar and check crew mix
The line item sidebar (the panel on the right) now shows the weighted crew mix per task. For a task that draws from two assemblies (e.g., wall pour using both the form crew and the finishing crew), you'll see something like "66% 3-person crew · 34% 4 finishers."
This tells you at a glance whether a parallel task is over-allocating the same crew. If two tasks both need your 4-finisher crew on the same day, the schedule is overcommitted. Stagger them.
Step 5 — Set a baseline before the job starts
Once the schedule looks right, click Set Baseline. This snapshots the current plan. Every future change is compared against the baseline so you can see drift as the job runs.
Step 6 — Print the lookahead
Click Reports → Two-Week Lookahead. You'll get a clean printable PDF that shows the tasks active in the next 14 days, the crew assignments, and any critical-path items. Hand it to the superintendent.
That's the loop. Estimate → Schedule → Lookahead → Field. Under 10 minutes from a priced estimate to a field-ready Gantt.
Common pitfalls
- No crew assigned. If a line item has no crew, the generator defaults to a 2-person crew at 1.0x productivity. Always assign a real crew.
- Quantity in the wrong unit. Wall LF priced as SF will give you a duration that's off by an order of magnitude. Watch the units.
- Inspection holds not in the schedule. Add inspection tasks manually with a fixed 1–2 day duration and link them as FS predecessors to the next pour.