Labor productivity defaults that won't get you in trouble

Industry-standard productivities are a starting point, not a bid. Here's how to use them — and when to override.

What productivity actually means

Productivity is hours per unit. 0.05 manhours / SF on a slab on grade is one carpenter doing 20 SF an hour. Industry tables — RSMeans, Walker's, Concrete Construction Magazine references — give you a defensible starting point.

The mistake is treating them as a bid. They're a starting point. The bid is what your crew does on your jobs.

Where defaults work well

  • New scope you haven't bid before. Use the table.
  • Standard work in known conditions. Your slab on grade in a warehouse with good access is going to land within 10% of the table.
  • Sanity checking. If your bid is at 0.02 manhours / SF and the table is at 0.05, you have a problem. Either your crew is twice as fast as the industry (it isn't) or your bid is wrong.

Where defaults will burn you

  • Tight access. A downtown urban site with no laydown is not a 0.05 SF slab.
  • Cold weather pours. Add 15–25%.
  • High-rep formwork. Productivities improve with repetition. Tilt panel #20 is faster than tilt panel #2. Most tables don't account for this.
  • Decorative or architectural finishes. The table for a broom finish is not the table for a polished concrete floor with dye.

How Bedrock handles it

Every Bedrock assembly carries a default productivity that's editable per company. When you bid, you can override per estimate. The override is logged so you can review your assumptions on the post-mortem.

Use the table as a checkpoint. Bid your crew. They're not the average.