Field-verified production rates: the only number that matters in your cost database

Published unit prices are a starting point. The number that wins or loses your bid is what your crew actually puts in place. Here's how to build that loop.

Why published rates lie

Pick up any cost reference book and look up "place 5000 psi concrete, slab on grade." You'll find a number, maybe $185–$220 per cubic yard installed, with a labor productivity of around 0.45 manhours per cubic yard.

That number is an average. Average of what? Average of every job in every region with every crew composition in every weather window. It is correct exactly nowhere.

Your bid is not on every job. Your bid is on this job, with your crew, in your region. The published rate is a starting point. The number that actually decides whether you make money is the rate your crew actually puts in place.

What "field-verified" actually means

A field-verified rate is built from your own jobs. Three numbers feed it:

  1. 1.Quantity placed. Not the bid quantity. The quantity that was actually poured, set, or installed. Pulled from the delivery tickets or the foreman's daily.
  2. 2.Labor hours consumed. Pulled from the timecard, restricted to the cost code for that scope.
  3. 3.Calendar days that scope was active. Weather days excluded.

Production rate = quantity placed ÷ labor hours consumed.

Compare against your bid rate. The delta is the gap between what you priced and what you can actually do.

The loop that closes the gap

A typical cost database has hundreds of line items. You don't update all of them. You update the ones that drive your margin.

For a concrete contractor that's usually:

  • Slab on grade placement (CY/MH)
  • Wall formwork (SFCA/MH)
  • Footing placement (CY/MH)
  • Tilt panel cast (panel/MH)
  • Rebar install (LB/MH)

Five line items. Maybe ten. Track those five rates on every job. Update the database monthly with a rolling 6-job average.

After 18 months you stop using published rates entirely. Your numbers become better than anything you can buy.

What to do when field data disagrees with your gut

The foreman's gut says "we crushed it" and the data says you ran 0.62 MH/CY when you bid 0.45.

The data wins. Always. The foreman is comparing the job against the worst job he remembers. The data is comparing it against the job you priced.

When data disagrees with the bid:

  • Find out why it ran heavy. Was it dewatering? Inspector hold? Bad mix? Crew turnover?
  • If the cause is the scope itself (e.g., reinforcement was denser than the published rate accounts for), update the rate.
  • If the cause is the project (one-off weather event), note it but don't update.

Three jobs of data is a pattern. One job is a story.

Building the loop with Bedrock

In Bedrock, every estimate line item carries a cost code. Actual costs and hours flow back to the same code on the project budget. The variance — bid vs. actual — is the field-verified rate, ready to push back into the cost database.

You don't have to build this loop by hand on a spreadsheet. The loop is the product.

When you've run that loop on 30 jobs you stop guessing on bid day. You're not estimating anymore. You're forecasting.