The invitation that doesn't fit
You've built tilt walls for ten years. The GC you've worked with on six warehouses just sent you an invitation to bid on a 4-story podium-deck mixed-use. They want a number by Friday.
You can:
- 1.Pass.
- 2.Bid it like you'd bid a tilt — and pray.
- 3.Bid it like a job you've never built before — which is what it is.
Option 3 is harder than it sounds, and it's the only one that doesn't either cost you a customer or cost you money.
Step 1: Decide if you should bid at all
Three questions, answer honestly:
- Is the scope adjacent to what you actually do, or different? Adjacent means the methods, crews, and tools transfer with a learning tax — a structural slab contractor bidding a podium deck is adjacent. Different means you're renting a crew, leasing equipment you've never owned, and learning a code chapter at the same time. Adjacent is worth bidding. Different usually isn't.
- Do you have somebody to call? A retired superintendent, a buddy at another shop, a manufacturer's rep — somebody who'll spend 30 minutes on the phone telling you what the gotchas are. Without that lifeline, you're guessing.
- Can you walk away from the price if it comes in ugly? If you need this job to make payroll, you'll convince yourself the number is workable. That's how contractors go under.
If all three answers are yes, bid it. If any answer is no, send a polite "thanks for thinking of us, not our wheelhouse right now" — that's a relationship-builder, not a relationship-killer.
Step 2: Build the estimate from first principles
The trap is to take your familiar assemblies and shoehorn them in. Don't.
Instead, work backward from what the work actually requires:
- What goes in the ground first? Forming, rebar, embeds, pour sequence.
- What sets the schedule? Cure times, crane picks, deck shoring, MEP sleeves.
- What's the crew composition? A podium deck isn't a slab on grade. The labor mix is different. So is the productivity.
- What equipment is on site, and who pays for it? If the GC provides the crane, get that in writing before you price it out.
Build the assembly from the field operation, not from your library. Your library was tuned for jobs you've done. This one isn't on it yet.
Step 3: Price the unknown explicitly
This is the part most estimators get wrong. They add "10% for risk" to the bottom line and call it done. That's not risk pricing — that's anxiety pricing.
Instead, list the things you're guessing at. Out loud, on paper. For each one, decide whether it's:
- A learning tax — the crew will be slower the first time. Add 15–25% to labor hours on that scope.
- A scope unknown — you don't know what the spec actually requires. Carry an explicit allowance and call it out in your bid.
- A market unknown — you've never bought this material in this quantity. Get two real quotes before you bid; don't extrapolate from list price.
When you stack those numbers, the bid will land higher than it would if you'd shoehorned. That's correct. If the higher number doesn't win, you weren't going to make money on it anyway.
Step 4: Write the proposal so the GC understands the price
If you submit a low number with no notes, the GC assumes you're aggressive. If you submit a higher number with no notes, the GC assumes you're padded.
Write three lines in your bid summary:
"This proposal includes a 20% productivity allowance on deck pours, reflecting our crew's first project on this system. It excludes shoring design (assumed by GC). Material pricing is based on a written quote from [supplier] dated [date], valid 30 days."
That tells the GC you know what you're doing — even on a job you haven't done. It also gives them a reason to call you with questions instead of just comparing line items.
Step 5: After the bid, debrief
Win or lose, sit down on Monday and write down what you'd do differently. Three bullets. File it next to the bid.
The second time you bid this type of work, you start 80% of the way there. The third time, you're competitive. The fifth time, it's a normal job.
The estimators who get a new specialty every five years didn't have a secret. They just bid their first one honestly.