The sheets nobody reads
Open any commercial bid package. Find the structural typical-details sheet — usually S0.1 or S2.1, sometimes hidden in the back. Now ask three estimators what's on it. You'll get three different answers.
Typical details are the most under-read sheets in the set, and they almost always contain quantity-impacting requirements that no plan view shows. Skip them and you're either short-bidding the job or eating the difference in the field.
What lives on typical detail sheets
- Reinforcing patterns for footings, walls, slabs, and piers
- Dowel sizes, lengths, and spacing at construction joints
- Vapor barrier, cap rock, and base course depths
- Edge form requirements (chamfer, drip edge, tooled joints)
- Anchor bolt patterns and embed depths
- Waterproofing and damp-proofing extents
- Slab depressions and thickened slabs at equipment pads
None of this is on a plan view. All of it costs money.
The 20-minute process that catches 90% of it
Before you start your takeoff:
Minute 1–5. Pull every typical-detail sheet into one window. Note the sheet numbers. You'll come back to these.
Minute 5–12. Read each detail. For each one, write down (on paper, in a notes column, anywhere) the answer to: "Does this add a quantity I'd otherwise miss?"
Examples:
- "Typical footing has 3-#5 cont. top and bottom plus #4 ties at 12" OC." → That's rebar tonnage you wouldn't get from a plan.
- "Slab edge has 1/2" chamfer with 6" thickened edge." → That's extra formwork LF and CY beyond your slab area.
- "Construction joints at 30' OC max with #4 × 24" dowels at 12" OC drilled and epoxied." → That's labor hours and dowel material your slab quantity doesn't show.
Minute 12–18. Add the quantity adders to the relevant assemblies. Don't try to remember them at bid time.
Minute 18–20. Flag any detail that conflicts with a plan view or a spec section. Send an RFI now, not the day before bid.
The mistake that wastes the most money
The biggest typical-detail mistake isn't missing one. It's double-counting one. If your assembly already includes #4 ties at 12" OC, don't add them again from the typical detail. Decide once, in the assembly, where each line item gets its quantity. Then trust it.
Why this is faster in Bedrock
Bedrock assemblies have a "spec source" field. When you build a footing assembly, you can attach the typical detail sheet directly. Next time you're on a similar bid, the assembly remembers the source. You're not re-reading the same detail every six months.
The bid-day check
After your takeoff is done, open the typical-detail sheets one more time. Compare against your assembly list. If any line item on the detail doesn't appear somewhere in your quantities, you have a 10-minute decision: include it now or formally exclude it in the cover letter.