What's in the worksheet
Five tabs, locked formulas, editable inputs.
Tab 1: Spread footings
Inputs: footing length, footing width, footing depth, top bars EW spacing, bottom bars EW spacing, bar size.
Outputs: top mat LB, bottom mat LB, total LB per footing, total LB by count.
Tab 2: Continuous footings
Inputs: footing LF, top bars count, bottom bars count, bar size, corner bars count.
Outputs: total LB including corner bars and standard splice laps.
Tab 3: Walls
Inputs: wall LF, wall height, horizontal bar size, horizontal spacing, vertical bar size, vertical spacing.
Outputs: total LB horizontal, total LB vertical, total LB with hooks top and bottom.
Tab 4: Columns
Inputs: column count, column height, vertical bars count, vertical bar size, tie size, tie spacing (end zones and middle zones).
Outputs: total LB vertical, total LB ties, total LB per column, total LB project.
Tab 5: Slabs
Inputs: slab SF, mat layout (top, bottom, both), bar size each direction, spacing each direction.
Outputs: LF each direction, total LB.
How to use
- 1.Fill in the input cells (highlighted yellow).
- 2.Outputs auto-calculate.
- 3.Sum across tabs for the total project rebar.
- 4.Use this as your check against your assembly-driven estimate. They should agree within 5%.
Disagreements are a signal — either the spreadsheet is missing geometry or your assembly is. Investigate before submission.