What tilt-up actually is
For estimating, tilt-up is three problems stacked:
- 1.A casting slab with isolation membrane and chamfer screeds.
- 2.A panel program — variable size, openings, embeds, lift inserts, brace inserts.
- 3.A lift and brace sequence that costs more than most estimators put in their bid.
If you bid it like flatwork plus walls, you'll lose every tilt-up project to a contractor who bids it like an industrial process.
Casting slab vs. final slab
Most projects use the building slab as the casting bed. The casting work — chamfer screed, bond breaker, panel layout — is additional to the building slab cost. It's not the same line item. We see contractors miss this and undercut themselves by $0.30–$0.80 / SF on the slab scope.
Panels are not LF of wall
A 32' tall × 24' wide panel with two punched openings, four lift inserts, six brace inserts, and a roof embed is not a unit-rate item. It's a panel with parametric scope. Bedrock handles this with a panel assembly that takes height, width, opening SF, and embed schedule as inputs and derives concrete CY, rebar lb, embed lb, and forming hours.
The lift week
Crane day is the most expensive day on a tilt-up job. Mobilization, operator, signal, rigging, the whole-day rate. If you're bidding 60 panels and your sequence assumes 12 panels per crane day, you have five crane days. Miss the sequence by one day and you've eaten 20% of your panel scope margin.
Always model lift days as their own line. Always.