Five places rebar goes missing
Rebar is the line item that separates the contractor who knows their numbers from the one who hopes. Here are the five misses we see most often when we audit a contractor's spreadsheet bid.
1. Forgetting development length
Lap splices add 30–60 bar diameters per splice. A 60' wall with #5 horizontal at 16" OC isn't 45 bars × 60'. It's 45 bars × 60', plus splice laps, plus corner bars, plus dowels.
2. Using SF for slab rebar mat instead of LF both ways
A 50' × 100' slab with #4 at 18" OC each way isn't (50 × 100) × some lb/SF factor. It's (50 ÷ 1.5) × 100 ft of bar one way, plus (100 ÷ 1.5) × 50 ft of bar the other way. The unit math matters.
3. Treating column ties like a pour-in-place afterthought
A 24" × 24" column with #4 ties at 4" OC at the ends and 8" OC in the middle is two tie-spacing schedules. If your formula has one tie spacing, your tonnage is off by 12–18%.
4. Hook lengths in walls
#5 vertical wall bars hooked top and bottom add 12 bar diameters per hook. On a 12' wall with 60 bars, that's 60' of extra bar you've already cut and bent. It's in your supplier invoice. It needs to be in your bid.
5. Spirals on round columns
A spiral cage on a round pier isn't a tie line item. It's a continuous bar wrapped helically. The bar length is roughly π × diameter × turns. We see contractors bid spiral cages with the same lb/LF as a tied cage. They're not the same.
How Bedrock handles it
Each Bedrock assembly carries its own rebar formula — vertical, horizontal, ties, hooks, splices, spirals. You set the rebar schedule once per assembly. Every measurement that uses that assembly inherits the math. Tonnage is correct because the geometry is correct.
Most rebar errors aren't carelessness. They're spreadsheet limitations. Move the geometry out of the spreadsheet and the tonnage stops drifting.